Power Transformers for Iraq within 12 weeks

A world leading generator manufacturer emailed the contract engineering team with an urgent enquiry to manufacture six 15mVA power transformers and forty-seven 1600kVA distribution transformers for installation on site in Iraq.

The transformers were required to be installed within a very tight time frame. Our contract engineers responded with a 24h quotation and provided subsequent quotes based on a variety of client specifications. With exact requirements being finalised, we quoted for the equipment to be manufactured and ready for shipment within 14 weeks from approval of drawings.

With timely delivery of the equipment being crucial, we were able to cut project delivery time considerably: the first batch of transformers were manufactured within ten weeks and reached the site in only twelve weeks, enabling our client to start operations prior to schedule and laying the foundations for a successful partnership."